Excavation & Trenching

Excavation Over 4 Feet Deep

Excavation procedures for trenches over 4 feet with protective systems and competent person requirements.

Revision 2.1 Updated Jun 19, 2026

Scope and Purpose

This procedure sets out how to plan, dig, protect, inspect, work in and close out an excavation or trench that is 4 ft (1.22 m) deep or more, where anyone will go in.

Company rule: no one enters an excavation 4 ft (1.22 m) deep or more unless it is protected by a sloping, benching, shoring or shield system selected by the competent person, or is entirely in stable rock. This is stricter than both:

Hazard Identification

  • Cave-in
  • Surcharge loads at the edge (spoil, materials, machines, vehicles, nearby structures)
  • Falling material or equipment into the excavation
  • Struck by loads or digging equipment
  • Mobile equipment falling in or striking the edge
  • Underground utilities (gas, electric, water, sewer, telecom)
  • Hazardous atmosphere (low oxygen, flammable gas, toxic gas from landfill, sewers, fuel, engine exhaust)
  • Water in the excavation (groundwater, rain, broken pipe)
  • Collapse of adjacent buildings, walls, sidewalks or pavement
  • Falls into the excavation
  • Traffic
  • Shield moved with people inside
  • Failure of damaged shoring or shields

Required PPE

  • Hard hat.
  • Safety footwear.
  • Safety glasses.
  • High-visibility vest or garment. Required in the US when exposed to public vehicle traffic and in Canada federal workplaces where there is a risk from moving vehicles. Company floor: high-visibility apparel for everyone on site; class as set by the traffic control plan (Class 2 minimum near traffic).
  • Work gloves.
  • Personal gas monitor for at least one worker in the excavation (company rule), in addition to pre-entry testing.
  • Respiratory protection only as specified by the atmosphere assessment, under the employer's respiratory protection program.
  • Hearing protection where noise requires it.

Key Procedure Steps

Plan (before digging)

  1. Review the job: depth, width, length, how long it will be open, nearby structures, roads, previous backfill, water table, and whether the work could be done from the surface instead.
  2. Contact the one-call centre (811 in the US; your provincial one-call service in Canada) and utility owners within the notice period your state or provincial law sets, and wait for the locates.
  3. Remove or support surface hazards near the edge (poles, walls, boulders, trees).
  4. Name the competent / qualified person.
  5. Bring the tabulated data or design to the site.
  6. Plan spoil placement, equipment positions, egress points, pumps, traffic control and barricades.

Dig and protect

  1. Expose utilities near the marks by hand or vacuum excavation.
  2. Classify the soil as you dig using at least one visual and one manual test (US Appendix A).
  3. Install the protective system as the excavation goes down.
  4. Nobody is inside a shield while it is installed, removed or moved vertically.
  5. Install ladders, stairways or ramps so no worker travels more than 25 ft (7.62 m) to get out.
  6. Keep spoil, materials and tools at least 1 m (3.3 ft) back from the edge (company floor; US minimum 2 ft or retaining devices; Canada federal 1 m).
  7. Company floor: heavy equipment and vehicles not working the excavation stay back from the edge at least a distance equal to the excavation depth.
  8. Barricade the excavation.
  9. Divert surface water away from the excavation.

Before entry (each day and after any break in work)

  1. Competent person inspects the excavation, the area around it and the protective system for signs of distress, protective system problems, water and hazardous atmosphere, and completes the Pre-Work Checklist.
  2. Test the air before every entry at 4 ft or more (company rule), and again whenever conditions change: oxygen first, then flammable gas, then toxic gases, at the bottom where workers will be.
  3. Brief the crew: protected area limits, egress points, signs to get out, emergency roles.

Work

  1. Work only inside the protected area.
  2. Nobody stands under loads handled by lifting or digging equipment.
  3. The competent person re-inspects as needed during the shift, and after any rain, vibration source, new surcharge load, water seepage or other event that increases the hazard.
  4. Get out at once on any sign of distress, a gas alarm, rising water, shield or shoring movement, or when the competent person says so.

Close-out

  1. Remove tools and materials.
  2. Remove shoring from the bottom up, releasing members slowly and watching for failure.
  3. Pull shields only with everyone out.
  4. Inspect shoring, shields and ladders after removal; tag damaged parts out of service for the competent person to examine.
  5. Backfill, or cover and barricade the excavation if it stays open.

Each step is shortened to its first sentence. The full procedure, with every condition, checklist and sign-off field, is in the PDF.

Training Requirements

  • Competent person (US) / qualified person (Canada federal): Training and experience in soil classification (visual and manual tests), protective system selection and tabulated data, inspections, water and atmosphere hazards; authority to stop work and remove workers; named in writing by the employer.
  • Equipment operator: Licensed or certified for the machine as your jurisdiction requires; trained on locates and hand-digging zones, setbacks, signals and warning systems.
  • Workers who enter: This procedure: protected area only, egress, signs of distress, gas alarms, stay-out rule after a cave-in, emergency roles.
  • Gas tester: Training on the monitor used: bump test, calibration, testing order (oxygen, flammable, toxic), recording.
  • First aider: First aid and CPR certificate to the level your jurisdiction and site require.

Regulatory References

  • US OSHA 29 CFR 1926 Subpart P, Excavations: 1926.650 (definitions); 1926.651 (specific excavation requirements, incl. (b) utilities, (c)(2) egress, (g) hazardous atmospheres, (h) water, (i) adjacent structures, (j) loose rock and spoil, (k) inspections); 1926.652 (protective systems); Appendix A (soil classification); Appendix B (sloping and benching); Appendix F (selection; over 20 ft engineer design).
  • US OSHA 29 CFR 1926.1053(b)(1), portable ladder extension above the landing.
  • US OSHA 29 CFR 1904.39, Reporting fatalities, hospitalizations, amputations and losses of an eye.
  • Canada: COHSR SOR/86-304, Part III s. 3.12 (Excavation), Part XII (protection equipment) and Part XV (Hazardous Occurrence Investigation, Recording and Reporting), for federally regulated workplaces.
  • Provincial OHS regulations each have excavation and trenching requirements, and provincial law sets one-call notice periods. Use the ones for your province.
  • Named for reference, not quoted: CSA Z247, Damage prevention for the protection of underground infrastructure. Confirm the current edition.

Download the Full PDF Template

Get the complete Excavation Over 4 Feet Deep document as a fillable PDF, part of the Safe Work Procedures Template Pack.

Get Template Pack

Get This SWP + 4 More Free

Choose from 112 procedures. No credit card, no commitment.

Pick Your 5 Free SWPs

Want Digital Sign-Off for Your SWPs?

Make Safety Easy lets your crew acknowledge procedures on any device. Track who read what, when. No more lost paper forms.

Start Your Free Trial