Bulldozer / Dozer Operation
Bulldozer operation including slope assessment, edge work and rollover prevention.
What This Procedure Covers
- Authorize the work
For the identified track-type dozer and approved earthmoving task. Complete the local ground, traffic and service controls before operation; clearing, ripping and specialist work may require additional plans.
Check the actual operating environment: Identify people, other machines, overhead services, buried services, unsupported edges, hidden voids and unstable fill. Stop where conditions fall outside the approved work plan. Machine size and traction do not establish ground stability.
- Inspect before starting
Complete the manufacturer inspection and functional checks in a clear area. Inspect tracks, rollers, sprockets, blade and ripper connections, hydraulics, protective structures, access steps and visibility aids.
Safety functions must remain effective: Use the seat belt and maintain the protective structure in its approved condition. Do not bypass operator-presence, parking or implement-control safeguards. Machine features vary; confirm the functions fitted to this unit and their required checks. Use designated steps and handholds with three points of contact. Keep access surfaces clear of mud and ice. Inspect from safe positions; servicing and work beneath raised equipment require a separate authorized maintenance method.
- Assess ground, slopes and services
Set route and work limits from the actual machine manual and a competent site assessment. Do not use a generic 45-percent slope limit or one blade width as proof that an edge is safe.
Control contact with services: Confirm buried-service locations and approved ground-disturbance limits before blade or ripper penetration. Establish overhead electrical clearance for the voltage and jurisdiction across the entire machine and implement envelope; lowering the blade alone does not establish safe clearance. Reassess after rain, erosion, excavation changes or placement of new fill. Stop for cracks, settlement, sliding or unexpected ground resistance and obtain approval before restarting.
- Separate people and move deliberately
Establish work-zone boundaries and pedestrian routes. Reduce reversing where practical. Check the intended path before moving; alarms and cameras supplement the traffic plan and do not prove the area is clear.
Maintain control and visibility: Travel at a controlled speed with the blade and ripper in the manufacturer travel positions. Use smooth inputs and follow the approved slope direction and turning restrictions. Stop if visibility or communication is lost; never continue toward a person who has disappeared from view. Before authorized approach, stop movement and secure the machine and implements using the prescribed method. Do not allow riders or anyone inside a crushing zone between the dozer and another object.
- Doze within the approved plan
Use the selected blade and operating method for the material and task. Avoid excessive loading, track slip and abrupt changes in direction. Assistance systems do not replace monitoring the work area and ground condition.
Protect edges and people below: Do not push toward an unsupported edge or beneath an unstable face. Maintain the assessed setback and keep people out of the material fall area. Do not assume stopping the tracks short of the visible edge protects against collapse of an undercut bank. Select noise, dust and other exposure controls from the task assessment. Specify any respiratory protection through the applicable program rather than a generic instruction to wear a dust mask. Stop and report equipment damage, ground movement or service contact.
- Park and record
Use the designated stable parking area. Lower blade and ripper to the prescribed supported position, apply the parking brake, secure controls and complete the model shutdown sequence. Remove the key and prevent unauthorized use.
Reference guidance: Caterpillar dozer safety features and operating guidance; CCOHS Working Safely Around Heavy Equipment; applicable machine manual and local requirements. Site-specific approval is required.
Download the Full PDF Template
Get the complete Bulldozer / Dozer Operation document as a fillable PDF, part of the Safe Work Procedures Template Pack.
Get This SWP + 4 More Free
Choose from 112 procedures. No credit card, no commitment.
Pick Your 5 Free SWPsWant Digital Sign-Off for Your SWPs?
Make Safety Easy lets your crew acknowledge procedures on any device. Track who read what, when. No more lost paper forms.
Start Your Free Trial