Energized Electrical Work / Live Line

Procedures for energized electrical work with arc flash risk assessment and NFPA 70E permit requirements.

Revision 2.1 Updated Jun 19, 2026

Scope and Purpose

This procedure controls any task where a worker, tool or material will be on or near exposed electrical conductors or circuit parts that are energized or not yet proven dead. This includes troubleshooting, voltage testing, taking measurements, and the rare repair that cannot be done de-energized.

The default is always to de-energize, lock out and prove dead (see SWP Lockout / Tagout). Energized work is allowed only when:

Hazard Identification

  • Electric shock or electrocution from direct contact
  • Indirect contact through tools, ladders, long conductive objects
  • Arc flash (heat, light, molten metal)
  • Arc blast (pressure, flying parts, noise)
  • Fall or strike after involuntary muscle reaction
  • Contact caused by poor lighting or blind reach
  • Conductive jewelry or clothing
  • Defective rubber goods, tools or meters
  • Backfeed, induced voltage, stored energy (capacitors, UPS, generators, PV)
  • Fire from arc or overheated parts
  • Unqualified person entering the area

Required PPE

  • Rubber insulating gloves, class rated for the maximum voltage present, with leather protectors worn over them. Maximum use voltage (AC): Class 00 = 500 V, Class 0 = 1,000 V, Class 1 = 7,500 V, Class 2 = 17,000 V (29 CFR 1910.137 Table I-4). Glove label and test date must be legible.
  • Rubber insulating sleeves where the arms could contact other live parts.
  • Arc-rated shirt and pants or coverall, arc-rated face shield and balaclava or arc flash suit hood, at or above the label/study value (see SWP-058 for selection).
  • Non-melting underlayers (no polyester, nylon, acetate, rayon, polypropylene).
  • Safety glasses under the face shield.
  • Nonconductive, electrical-rated hard hat (look for the electrical class marking, Class E).
  • Hearing protection (inserts) when inside the arc flash boundary.
  • Leather work boots. Do not rely on footwear as the insulation from ground.
  • Insulated hand tools rated for the voltage. Company floor: 1,000 V rated tools for work at 600 V or less.

Key Procedure Steps

Set-up

  1. Confirm the job cannot be done de-energized.
  2. Complete the EEWP: description of work, reason it must be live, voltage, shock assessment, arc flash label/study value, PPE, approach limits, barricade location, attendant name, approvals.
  3. Get the EEWP approved and post it at the work location.
  4. Hold the job briefing with everyone named on the permit.
  5. Set barricades and signs at the arc flash boundary.
  6. Stage the rescue hook, AED, first aid kit and extinguisher on the exit side.
  7. Inspect and air-test rubber gloves; check the class and test date.
  8. Put on arc-rated PPE, gloves and face protection outside the boundary.

Work

  1. Stand to the side of the door or cover (hinge side where practical).
  2. Test the meter on a known live source, then measure.
  3. Cover live parts you are not working on with insulating blankets or covers rated for the voltage.
  4. Keep your body and tools outside the approach limit on the permit except for the part you are working on.
  5. Use insulated tools.
  6. Tell the attendant each step before you do it.
  7. Do not defeat an interlock unless it is part of the permit, and restore it as soon as the task is done.
  8. If anything changes (different voltage, unexpected source, damaged insulation, wet conditions, PPE damaged), stop, step back outside the boundary, and re-plan with the supervisor.

Close-out

  1. Remove tools, test leads and blankets in reverse order.
  2. Reinstall all covers and close doors before taking off arc-rated PPE.
  3. Take down barricades only after covers are on.
  4. Record the work done and any defects found on the EEWP. Close the permit with the supervisor.
  5. Inspect and store gloves, protectors and arc-rated clothing.

Each step is shortened to its first sentence. The full procedure, with every condition, checklist and sign-off field, is in the PDF.

Training Requirements

  • Qualified worker: Trade qualification for the equipment and voltage.
  • Attendant / safety watcher: Current CPR/AED and first aid certificate.
  • Supervisor / approver: This SWP, the EEWP form, how to read arc flash labels and the study, and when to refuse a permit.

Regulatory References

  • 29 CFR 1910.331 to 1910.335 (Subpart S electrical safety-related work practices), incl. 1910.332 Training, 1910.333 Selection and use of work practices, 1910.334(c) Test instruments, 1910.335 Safeguards for personnel protection
  • 29 CFR 1910.137 Electrical protective equipment
  • 29 CFR 1910.132(d) PPE hazard assessment
  • 29 CFR 1910.269 (power generation, transmission and distribution only)
  • 29 CFR 1926.416, 1926.417 (construction electrical); 1926.95, 1926.97 (construction PPE and electrical protective equipment); 1926.960 (construction power T&D only)
  • Canada Labour Code Part II, incl. s.128 (refusal to work)
  • Canada Occupational Health and Safety Regulations SOR/86-304, Part VIII Electrical Safety (ss.8.1 to 8.23 and Schedule); Part XII Protection Equipment
  • Provinces and territories have their own OHS regulations; check the one that applies to the work site.

Download the Full PDF Template

Get the complete Energized Electrical Work / Live Line document as a fillable PDF, part of the Safe Work Procedures Template Pack.

Get Template Pack

Get This SWP + 4 More Free

Choose from 112 procedures. No credit card, no commitment.

Pick Your 5 Free SWPs

Want Digital Sign-Off for Your SWPs?

Make Safety Easy lets your crew acknowledge procedures on any device. Track who read what, when. No more lost paper forms.

Start Your Free Trial