Excavation Near Structures
Excavation near existing structures with foundation protection and settlement monitoring.
Scope and Purpose
This procedure covers planning, digging, monitoring and backfilling excavations next to or under existing buildings, retaining walls, bridge abutments, foundations, sidewalks, pavement, poles, towers and other structures, where the work could make the structure move, settle or collapse onto workers or the public.
Use this SWP when either company screening test is met (company rule): 1. Any part of the excavation goes below a line drawn down and away from the bottom outside edge of the footing at 1 horizontal to 1 vertical (45 degrees); or 2. The structure is within a horizontal distance from the excavation edge equal to the excavation depth.
Hazard Identification
- Structure settles, tilts or collapses into the excavation
- Undermining of a footing, sidewalk or pavement
- Surcharge from the structure on the excavation walls
- Cave-in of the excavation (soil next to structures is often disturbed backfill)
- Vibration from equipment, compaction or pile driving
- Dewatering lowers groundwater under the structure
- Spoil, materials or equipment loading the zone
- Utilities under, attached to or entering the structure
- Falling debris from the facade, parapets or roof edges
- Occupants and public near the work
- Falls into the excavation
- Hazardous atmosphere (gas from a damaged service line, sewer gas)
Required PPE
- Hard hat. US: ANSI Z89.1 (1926.100). Canada federal: CSA Z94.1 or ANSI Z89.1 (COHSR 12.1).
- Safety footwear (Canada federal: CSA Z195, COHSR 12.11).
- Safety glasses (US 1926.102; Canada federal: selected per CSA Z94.3, COHSR 12.12).
- High-visibility apparel. Required in the US when exposed to public vehicle traffic (1926.651(d)) and in Canada federal workplaces where there is a risk from moving vehicles (CSA Z96, COHSR 12.17). Company floor: high-visibility apparel for everyone on site; Class 2 minimum near traffic (as SWP-061).
- Work gloves.
- Hearing protection where equipment noise requires it (US 1926.52, 1926.101).
- Respiratory protection only where the assessment calls for it, under the respiratory protection program.
Key Procedure Steps
Assess (before digging)
- Collect the structure information: drawings, footing depths and type, geotechnical report, building records, utility entries.
- Apply the two company screening tests (Section 1).
- Do the pre-construction survey of the structure: photos, crack map, measurements, dated.
- Notify the structure owner about the work, the survey and the monitoring (project rule).
Conditions for digging next to or below a footing
- Where the stability of a building, wall or other structure is endangered by the excavation, install support systems (shoring, bracing or underpinning) to keep the structure stable (US 1926.651(i)(1)).
- US: do not dig below the level of the base or footing of any foundation or retaining wall that could reasonably be expected to pose a hazard unless: (i) a support system such as underpinning is provided; (ii) the excavation is in stable rock; (iii) a registered PE has approved that the structure is far enough away to be unaffected; or (iv) a registered PE has approved that the work will not pose a hazard to employees (1926.651(i)(2)).
- Company rule (all sites, including Canada federal): below footing level only with a PE-designed support system installed, or a PE's written determination under (iii) or (iv).
- Do not undermine sidewalks, pavement or similar structures unless a support system or other protection is in place (US 1926.651(i)(3); company floor everywhere).
- Support systems must be designed (US 1926.652(c)): manufacturer's tabulated data, other PE-approved tabulated data, or a written PE design naming the PE, with a copy on site while it is built.
Protect the workers
- Put in a protective system for the excavation itself per SWP-061 (company floor 4 ft / 1.22 m), SWP-062 or SWP-063.
- Sloping near a structure: do not use Appendix B slopes until the structure's surcharge has been evaluated under 1926.651(i) (Appendix B (c)(3)(iii)).
- Timber shoring near a structure: Appendix C tables are not adequate where loads from structures within a horizontal distance equal to the trench depth exceed the load of a 2 ft soil surcharge (Appendix C (d)(2)(ii)(A)).
- Canada federal: in an excavation or trench more than 1.4 m deep with sides at 45 degrees or more, the walls are supported by shoring and bracing installed as the excavation is dug, or a movable steel plate and bracing system from ground level to the bottom; installed and removed by or under a qualified person (COHSR 3.12(3) to (5)).
Dig
- Install the structure's underpinning or support before digging to depths that affect the footing, in the engineer's sequence.
- Dig in the engineer's sequence and lift depths only.
- Keep spoil, stockpiles and parked equipment out of the screening zone unless the engineer allows it (company rule).
- Use sheet piling, soldier piles and lagging, secant walls or other engineered walls where the face next to the structure must be vertical, as the engineer designs.
- No vibratory compaction, breaking or pile driving inside the zone unless the engineer has assessed vibration and monitoring is running.
- Keep drainage running away from both the excavation and the footing.
Monitor
- Read the instruments at the frequency in the monitoring plan, and at least daily while digging or backfilling inside the zone (company floor), and after rain, a vibration event, or any sign of movement.
- At the engineer's action value: tell the supervisor and engineer at once and follow the engineer's instructions.
- At the engineer's stop value, or any visible movement: stop digging, get everyone out of the excavation, keep people out from under the structure's overhangs, and call the engineer.
- The competent person inspects the excavation, adjacent areas, structure and supports before each shift, as needed during the shift and after every rainstorm or other hazard-increasing event (US 1926.651(k)(1)).
Backfill and restore
- Backfill as soon as the work allows, to restore lateral support, in the sequence the engineer sets.
- Compact in lifts to the specification, with non-vibratory or engineer-approved equipment inside the zone.
- Keep reading the instruments during and after backfill until the engineer says they have stabilized.
- Do the post-construction survey and compare it with the baseline.
Each step is shortened to its first sentence. The full procedure, with every condition, checklist and sign-off field, is in the PDF.
Training Requirements
- Competent person (US) / qualified person (Canada federal): As SWP-061, plus: reading the engineer's drawings, sequence and monitoring plan; signs of structure distress; the Section 8 conditions for digging below a footing.
- Monitoring technician: Use of the instruments in the monitoring plan, reading and recording, action and stop values, who to call.
- Equipment operator: As SWP-061, plus: the dig sequence, no vibratory work inside the zone without approval, setbacks.
- All workers in or near the excavation: This SWP: protected areas, signs of structure movement, stop-work triggers.
Regulatory References
- 29 CFR 1926 Subpart P: 1926.650 (definitions incl. support system, registered professional engineer, stable rock); 1926.651 ((a) surface encumbrances, (b) underground installations, (d) traffic, (i) stability of adjacent structures, (k) inspections, (l) walkways); 1926.652 ((a) protection, (c) design of support systems, (d) materials, (e) installation and removal); Appendix B (c)(3)(iii); Appendix C (d)(2)(ii)(A).
- 29 CFR 1926.21(b)(2) (training); 1926.52, 1926.100, 1926.101, 1926.102 (PPE).
- 29 CFR 1904.39 (reporting).
- COHSR SOR/86-304: Part III s. 3.12 (excavation), Part XII (PPE: 12.1, 12.11, 12.12, 12.17), Part XV (15.5, 15.8 reporting), Part XIX (19.6 training). COHSR has no rule for adjacent structures; this SWP applies the US 1926.651(i) conditions as a company floor.
- Provincially regulated work: follow your province's excavation regulation and the local building code for protection of adjoining property.
Download the Full PDF Template
Get the complete Excavation Near Structures document as a fillable PDF, part of the Safe Work Procedures Template Pack.
Get This SWP + 4 More Free
Choose from 112 procedures. No credit card, no commitment.
Pick Your 5 Free SWPsWant Digital Sign-Off for Your SWPs?
Make Safety Easy lets your crew acknowledge procedures on any device. Track who read what, when. No more lost paper forms.
Start Your Free Trial