Scope and Purpose

This procedure sets out how trained crews identify, contain, remove, enclose, encapsulate, clean up and dispose of asbestos-containing material (ACM) so that workers, other trades and the public do not breathe asbestos fibres.

Only workers trained for the class (US) or risk level (Canada) of the work may disturb asbestos. If you are not trained for it, do not cut, drill, sand, scrape, break, remove, sweep or vacuum suspect material. Stop, keep people away, and tell your supervisor.

Hazard Identification

  • Disturbing ACM nobody knew about
  • Breathing asbestos fibres during removal of TSI or surfacing material (Class I; Canada high-risk)
  • Fibres escaping to other areas or the outside air
  • Dry methods, power tools, compressed air
  • Flooring removal (Class II)
  • Roofing, siding and transite removal (Class II)
  • Gaskets and other Class II material
  • Repair and maintenance that disturbs ACM (Class III)
  • Glove bag failure
  • Contamination carried out on clothing, skin, tools and containers (take-home exposure)
  • Wrong, damaged or poorly fitted respirator
  • Loss of negative pressure (machine failure, power loss, filter loading)
  • Electric shock in a wet enclosure
  • Heat stress in suits, respirators and enclosures
  • Falls from ladders, scaffolds, roofs and openings
  • Slips on wet sheeting
  • Fire (plastic sheeting, solvents, encapsulants, lighting)
  • Smoking
  • Waste handling and transport

Required PPE

  • No filtering facepiece (dust mask) respirator is ever used for asbestos.
  • Fit tested before first use, on any change of make, model, style or size, and at least annually (1910.134(f)(2)).
  • Nobody is assigned to asbestos work needing a respirator if the examining physician says they cannot wear one (US (h)(2)(ii)).
  • Disposable full-body coveralls with hood, foot coverings and gloves. Required by law in the US when exposure is above an exposure limit, when there is no required NEA, and for Class I removal of more than 25 linear ft or 10 sq ft ((i)(1)). Company rule: worn for all Class I and II work and for Canada moderate- and high-risk activity.
  • Inner gloves under outer gloves where hands contact wet ACM (company rule).
  • Rubber boots that can be washed in decontamination.
  • Eye protection where a half-mask is worn (the full facepiece covers the eyes).
  • Hard hat where there is overhead work or falling material.
  • Hearing protection where the noise assessment requires it.
  • Fall protection per SWP-004.

Key Procedure Steps

Plan and identify

  1. Get the owner's asbestos information and the survey.
  2. Classify the work (US Class I to IV; Canada low/moderate/high-risk by a qualified person).
  3. Give the agency notice and get permits where required.
  4. Tell the owner, other employers and their workers what is there and how it will be contained.

Set up

  1. Mark the regulated area.
  2. Shut down, lock out (SWP-001) and seal the HVAC with a double layer of 6-mil plastic.
  3. Pre-clean the area with a HEPA vacuum and wet wiping.
  4. NPE: line floors and walls with two layers of 6-mil (company rule).
  5. Build the decontamination area (equipment room, shower, clean room in a row) for Class I jobs over 25 linear ft or 10 sq ft.
  6. Competent person makes the initial exposure assessment.

Enter

  1. Enter through the clean room.

Remove: Class I (TSI and surfacing material)

  1. Wet the material with amended water before and during removal.
  2. Remove in small sections.
  3. Bag waste at once while still wet.
  4. Glove bags: install around the full circumference, smoke-test, remove, wash debris to the bottom, encapsulate exposed material, collapse with the HEPA vacuum, seal and bag.

Remove: Class II (other ACM)

  1. Flooring: do not sand.
  2. Roofing: remove intact as far as feasible.
  3. Siding and transite: spray each panel with amended water.
  4. Gaskets: remove whole and place in a container at once; use a glove bag if the gasket is deteriorated; scrape residue wet.
  5. Other Class II material: wet thoroughly, remove intact, no cutting or breaking unless other methods are not feasible, bag or wrap by the end of the shift.

Repair and maintenance: Class III

  1. Use wet methods and local exhaust where feasible.

During the work

  1. Competent person inspects (Class I at least every shift) and checks the enclosure, pressure, suits and work practices.
  2. Take daily personal air samples representative of each worker in the regulated area doing Class I or II work (US).
  3. Mend or replace any torn suit at once.
  4. Clean up dust and debris with a HEPA vacuum or wet methods frequently, at the end of every shift and when the work is finished.

Exit (every time)

  1. In the work area, remove gross debris from your suit (HEPA vacuum or wet wipe).
  2. In the equipment room, take off the suit and put it in a labelled bag.
  3. Shower.
  4. Enter the clean room and dress in street clothes.
  5. Canada federal: wash hands and face before leaving the contaminated work area (10.26.6(2)).

Final clean-up and clearance

  1. Remove all ACM. HEPA-vacuum and wet-wipe every surface and the inner layer of sheeting.
  2. Competent person does a visual inspection.
  3. Apply lockdown encapsulant to surfaces where the specification calls for it.
  4. Clearance air sampling inside the enclosure, using forced air to keep fibres airborne (Canada federal 10.26.9(2)).
  5. Pass only when every sample meets the company floor (0.01 f/cc or less by PCM) and any stricter jurisdiction or specification limit.
  6. Remove the inner layers and critical barriers only after clearance.

Waste and close-out

  1. Wet the waste.
  2. Wet-wipe or HEPA-vacuum every container before it leaves the work area.
  3. Transport in marked vehicles to an approved disposal site.
  4. Within 10 days, tell the owner and following employers what ACM is left and give them the final monitoring results (US).

Each step is shortened to its first sentence. The full procedure, with every condition, checklist and sign-off field, is in the PDF.

Training Requirements

  • Class I worker; Class II worker using critical barriers or an NPE (US): Training equal in curriculum, method and length to the EPA Model Accreditation Plan (MAP) asbestos abatement worker course (1926.1101(k)(9)(iii)): at least 4 days of 8 hours, with at least 14 hours hands-on, respirator fit testing and an exam (40 CFR 763 Subpart E Appendix C).
  • Class II worker on roofing, flooring, siding, ceiling tile or transite (US): At least 8 hours with hands-on practice in the work practices for each material category and each removal method used ((k)(9)(iv)).
  • Class III worker (US): At least 16 hours with hands-on practice, consistent with EPA's training for school maintenance and custodial staff ((k)(9)(v)).
  • Class IV worker (US): At least 2 hours of awareness training, including where ACM and PACM are in the building and how to recognize damage ((k)(9)(vi)).
  • Water spray process operator (US): An extra 40-hour course in the process, on top of Class I training ((g)(5)(v)).
  • Competent person, Class I and II (US): Comprehensive supervisor course meeting the EPA MAP (at least 5 days) ((o)(4)(i); Appendix C).
  • Competent person, Class III and IV (US): Course consistent with EPA's training for school maintenance staff (40 CFR 763.92(a)(2)), covering glove bags, mini-enclosures, wet methods, the standard and asbestos identification ((o)(4)(ii)).
  • NESHAP on-site representative (US): Trained in the NESHAP rules and how to comply with them (61.145(c)(8)).
  • Canada federal: anyone doing or supervising the work: The employer's asbestos education and training program (COHSR 10.26.2(f), 10.14).
  • Person taking air or clearance samples: Qualified person, competent in NIOSH Method 7400 (PCM) sampling, the method COHSR 10.26.9 names.
  • All respirator users: Respirator training and fit test under the respiratory protection program (1910.134).

Regulatory References

  • US OSHA 29 CFR 1926.1101, Asbestos (construction), including (b) definitions, (c) exposure limits, (d) multi-employer worksites, (e) regulated areas, (f) exposure assessment, (g) methods of compliance, (h) respiratory protection, (i) protective clothing, (j) hygiene facilities, (k) communication of hazards and training, (l) housekeeping, (m) medical surveillance, (n) recordkeeping, (o) competent person, Appendix F (non-mandatory work practices).
  • US OSHA 29 CFR 1910.1001, Asbestos (general industry). Named.
  • US OSHA 29 CFR 1910.134, Respiratory protection (Table 1 assigned protection factors; fit testing; training).
  • US OSHA 29 CFR 1904.39, Reporting fatalities, hospitalizations, amputations and losses of an eye.
  • US EPA 40 CFR 61 Subpart M, 61.145 (demolition and renovation) and 61.150 (waste disposal).
  • US EPA 40 CFR 763 Subpart E (schools; Model Accreditation Plan, Appendix C; clearance 763.90(i)). Applies directly to schools; used here for training and clearance references.
  • Canada: COHSR SOR/86-304, Part X ss. 10.1, 10.4 to 10.6, 10.14, 10.19, 10.26.1 to 10.26.11; Part XII s. 12.13; Part XV s. 15.5 (federally regulated workplaces).
  • CSA Z94.4 (respirators). Named only.
  • Provincial asbestos regulations and US state asbestos programs. Use the ones for your location.

Download the Full PDF Template

Get the complete Asbestos Abatement document as a fillable PDF, part of the Safe Work Procedures Template Pack.

Get Template Pack

Get This SWP + 4 More Free

Choose from 112 procedures. No credit card, no commitment.

Pick Your 5 Free SWPs

Want Digital Sign-Off for Your SWPs?

Make Safety Easy lets your crew acknowledge procedures on any device. Track who read what, when. No more lost paper forms.

Start Your Free Trial