Elevator / Hoist Installation

Elevator and hoist installation with hoistway protection, fall arrest and car-top procedures.

Revision 2.1 Updated Apr 19, 2026

Scope and Purpose

This procedure covers work in and around hoistways during the installation and modernization of elevators, and the erection, use, inspection and dismantling of temporary construction hoists.

Covers:

Hazard Identification

  • Fall into an open hoistway at a landing
  • Fall inside the hoistway (car top, false car, platforms, rail setting)
  • Falling objects down the hoistway
  • Struck or crushed by the moving car or counterweight
  • Uncontrolled car or counterweight movement (brake, rope or safety failure)
  • Rigging failure lifting machines, rails or the car
  • Electrical shock or arc flash (controller, machine, temporary power)
  • Moving machinery (sheaves, ropes, drive)
  • Construction hoist: car falls, worker falls at a landing, struck by tower or car
  • Pit hazards: water, confined atmosphere, stored material
  • Hot work in the hoistway (welding rail brackets, cutting)
  • Poor lighting

Required PPE

  • Full-body harness (no body belts for fall arrest), with an energy-absorbing lanyard or self-retracting lifeline suited to the clearance available. Two lanyards or a twin-leg lanyard for 100% tie-off (company rule).
  • Rope grab and vertical lifeline where vertical lifelines are used, one per worker (see section 4 for the false-car exception).
  • Hard hat with chin strap (site rule).
  • Safety glasses; face shield or welding protection for hot work.
  • Gloves suited to the task (wire rope, rails, steel).
  • Safety footwear.
  • High-visibility apparel where equipment operates or on landings shared with other trades.
  • Electrical PPE as required by SWP-052 / Arc Flash SWP-058 for energized testing.
  • Hearing protection where noise requires it.

Key Procedure Steps

8.1 Before work

  1. Confirm the permit, the licensed crew where required, and the manufacturer's instructions.
  2. Walk every floor.
  3. Check temporary lighting in the hoistway and pit (US: at least 5 foot-candles) and the machine room (US: at least 10 foot-candles), and GFCI on temporary power.
  4. Brief the crew on the day's tasks, anchors, communication and the rescue plan.

8.2 Barricades and openings

  1. Only the elevator crew removes a barricade, one opening at a time, and only for the task.
  2. Anyone working at or leaning through an open opening is tied off to an anchor set back from the opening (US rule where the guardrail is removed for hoisting; company rule always).
  3. An attendant stays at an open opening to keep others away (company rule).
  4. Openings used for passing materials: a chain, gate or removable section across the opening whenever hoisting is not taking place.
  5. Holes and pit covers: secured, marked "HOLE" or "COVER", and strong enough for twice the load they may carry.

8.3 Working in the hoistway

  1. Tie off whenever exposed to a fall of 4 ft (1.2 m) or more (company floor).
  2. Use anchors rated 5,000 lb per worker, or designed by a qualified person with a safety factor of at least 2.
  3. Keep 100% tie-off when moving between anchors (two lanyards or a twin-leg lanyard).
  4. Work from the false car or a platform with guardrails where possible.
  5. Do not work below another crew in the same hoistway unless a protective deck or overhead protection is in place.
  6. Lifting machines, rails and components: use the rated, marked lifting beam and rated rigging.
  7. Hot work: permit, fire watch, and check the floors above and below.

8.4 Car and counterweight

  1. Before entering the pit or working in the path of the car or counterweight, block them or lock out the machine and controller under SWP-001.
  2. Keep the counterweight secured until the manufacturer's sequence allows release.
  3. Never put any part of your body between the car or counterweight and the hoistway wall, divider beam or any fixed structure.
  4. Move the car only on inspection operation, controlled by one person, with spoken confirmation from everyone in the hoistway before each move.
  5. Do not ride the car or a platform under power until the safeties, governor, buffers and interlocks for that configuration have been installed and tested per the manufacturer.

8.5 Electrical work

  1. Work on the controller, machine and circuits is done de-energized under SWP-001 by a qualified person.
  2. Label disconnects and controllers.
  3. Before energizing for the first time, the qualified person checks wiring, connections and safety circuits per the manufacturer and the electrical code that applies (US NFPA 70 Article 620; Canada CSA C22.1).

8.6 Construction hoists

  1. Erect the hoist to the manufacturer's instructions.
  2. Personnel hoists (US): anchor the tower to the structure at intervals not exceeding 25 ft, with guys as the rule requires; enclose the tower as 1926.552(c)(1), (c)(2) require; hoistway doors at least 6 ft 6 in high with locks that cannot be opened from the landing.
  3. Material hoists (US): landing bars or gates full width, latched, painted in diagonal contrasting stripes; bars of 2 x 4 or equivalent, 2 ft back from the hoistway line, 36 to 42 in high; overhead covering on the car and over the operator station; car arresting device.
  4. Before service, inspect and test all functions and safety devices under the supervision of the competent person (US) or by a qualified person (Canada federal).
  5. Post the rated load, speed and warnings on the car.
  6. Nobody rides a material hoist, except to inspect or maintain it (US).
  7. Never load a hoist or elevating device beyond its rated or safe working load.
  8. Operator has a clear view of the landing or works with a signaller.

8.7 Close-out and turnover

  1. Test all safety devices (governor, safeties, buffers, door interlocks, terminal stopping devices, emergency stop) per the manufacturer before turnover.
  2. The acceptance inspection required by the authority having jurisdiction is completed before the elevator is used by others.
  3. Hoistway barricades come down only when each hoistway door is installed, closed and interlocked.
  4. Dismantling a construction hoist: reverse of erection per the manufacturer, top down, tie-ins removed only as each section comes off; barricade the area below.
  5. Remove lockouts only under SWP-001, after everyone is clear.

Each step is shortened to its first sentence. The full procedure, with every condition, checklist and sign-off field, is in the PDF.

Training Requirements

  • Elevator mechanic / constructor: Licence or certificate where the jurisdiction requires it; the manufacturer's installation procedures for this unit; hoistway fall protection and rescue; car-top and inspection operation; LOTO SWP-001.
  • Apprentice / helper: Fall protection; barricade control; communication and signals; LOTO awareness.
  • Elevator foreman / supervisor: All of the above; installation sequence planning; rigging; the inspection and testing the jurisdiction requires before use.
  • Construction hoist erector / inspector: The manufacturer's erection, tie-in, inspection and testing procedures.
  • Construction hoist operator: The hoist's controls, rated load, operating rules and signals.
  • Rescue person / team: Trained on the rescue method and equipment in the plan for this hoistway; first aid and CPR.

Regulatory References

  • US OSHA 29 CFR 1926.552 (material hoists, personnel hoists and elevators).
  • US OSHA 29 CFR 1926.501(b)(3), (b)(4), (b)(14) (hoist areas, holes, wall openings) and 1926.502(b), (d), (i) (guardrails, personal fall arrest incl. elevator shaft lifelines, covers).
  • US OSHA 29 CFR 1926.417 (lockout and tagging of circuits). 29 CFR 1910.147 applies to general industry servicing and maintenance, not construction.
  • US OSHA 29 CFR 1926.56 (illumination), 1926.251 (rigging), 1926.1400 (cranes in construction, scope), 1926.21(b)(2) (training), 1904.39 (reporting).
  • Canada: COHSR SOR/86-304, Part II ss. 2.5, 2.12, 2.13 (openings, guardrails, toe boards); Part IV ss. 4.1 to 4.7 (elevating devices); Part XII ss. 12.06, 12.07, 12.09, 12.2 (fall protection, training); Part XIV ss. 14.20, 14.23, 14.24, 14.30, 14.43 (materials handling equipment); Part VIII and s. 13.16 (isolation, lockout); Part XV s. 15.5 (reporting) (federally regulated workplaces).
  • ASME A17.1 / CSA B44 (safety code for elevators), ASME A17.2 (inspection), ANSI A10.4 (personnel hoists), ANSI A10.5 (material hoists), NFPA 70 Article 620, CSA C22.1. Named only; check the edition your jurisdiction requires.
  • State and provincial elevator licensing, permit and inspection rules, and provincial OHS regulations. Use the ones for your location.
  • Manufacturer's installation, erection and testing instructions for the unit or hoist in use.

Download the Full PDF Template

Get the complete Elevator / Hoist Installation document as a fillable PDF, part of the Safe Work Procedures Template Pack.

Get Template Pack

Get This SWP + 4 More Free

Choose from 112 procedures. No credit card, no commitment.

Pick Your 5 Free SWPs

Want Digital Sign-Off for Your SWPs?

Make Safety Easy lets your crew acknowledge procedures on any device. Track who read what, when. No more lost paper forms.

Start Your Free Trial