Rebar Tying and Placement
Reinforcing steel placement, tying and impalement protection per OSHA requirements.
What This Procedure Covers
- Define the installation
For receiving, placing and tying reinforcing steel. Use current structural drawings and approved erection and lifting plans. This procedure does not authorize changes to reinforcement, temporary supports or lifting arrangements.
Protect everyone who can reach the work area: Assess projecting steel at floor level and beneath adjacent elevated work. Include other trades, delivery crews and access routes. Keep unprotected hazards inaccessible until the approved protection and safe access are installed.
- Select genuine impalement protection
Choose a protection system suitable for the bar size, orientation, fall exposure and local requirements. Check its instructions, intended use and any required approval before installation.
Cap shape is not proof of protection: Ordinary plastic mushroom caps may reduce scratches but do not provide impalement protection. Use a system specifically suitable for the assessed impalement hazard. Do not improvise a cover from loose plywood or assume a general product label covers every fall height and configuration. Follow the approved design for site-built protective troughs. Do not bend, cut or otherwise change structural bars without design authorization. Maintain protection throughout the work; when access or fall exposure changes, reassess the system before work continues.
- Receive, store and lift safely
Place bundles on stable supports and restrain them against rolling or sliding. Keep handling routes and walkways clear. Check bundle weight, balance and lifting arrangements before movement.
A tied cage is not automatically safe to lift: Confirm the cage has been designed and prepared for the planned lift. Use the specified lifting points and rigging; do not lift by ordinary tie wire or shipping bands. Keep people out from beneath suspended loads and clear of pinch points as the load is positioned. Base handling decisions on actual weight, length, reach and route, rather than bar number alone. Use aids to reduce force and awkward carrying. Keep long bars clear of electrical hazards and adjacent workers. Do not wrap a load-control line around the body.
- Place, support and tie in sequence
Install chairs, spacers, ties and temporary supports to the approved drawings and sequence. Keep vertical cages and wall reinforcement stable throughout erection, not only when assembly is complete.
Do not rely on the cage as an access or anchor system: Use designated safe access and working platforms. Do not climb unsecured reinforcement or attach fall protection to steel that has not been approved for that purpose. Confirm rescue arrangements where the fall-protection plan requires them. Follow tool instructions and keep hands clear of tying, cutting and bending mechanisms. Handle cut ends and tie-wire tails to prevent punctures. Do not alter braces or supports to improve access; stop and obtain approval if the planned method cannot be followed.
- Reduce strain and maintain the work area
Assess repetitive hand work, stooping, kneeling and carrying. Select tools and work positions that reduce force and awkward posture; review their suitability with the people doing the task.
Use controls that reduce the exposure: Powered tying tools and suitable extensions can reduce wrist motions and bending. Confirm their ties meet the specified pattern and strength; a powered tie is not interchangeable with every hand tie. Train users and vary tasks to reduce exposure. Encourage early reporting of pain, tingling or loss of grip. Keep loose wire, offcuts and displaced materials out of access routes. Recheck supports and impalement protection after handling, weather or other work that could disturb them. Coordinate the final inspection with the concrete crew before placement.
- Inspect and hand over
Record the installed area and remaining restrictions. Confirm reinforcement and temporary support acceptance with the responsible person; communicate protection that must remain during subsequent work.
Reference guidance: OSHA rebar-cap interpretation and 1926.703; CCOHS Working Safely Near Rebar; FPS Reinforcement and Pile Cages; University of Waterloo rebar-tying guidance. Local approval required.
Download the Full PDF Template
Get the complete Rebar Tying and Placement document as a fillable PDF, part of the Safe Work Procedures Template Pack.
Get This SWP + 4 More Free
Choose from 112 procedures. No credit card, no commitment.
Pick Your 5 Free SWPsWant Digital Sign-Off for Your SWPs?
Make Safety Easy lets your crew acknowledge procedures on any device. Track who read what, when. No more lost paper forms.
Start Your Free Trial