0
Construction Specialty

Formwork and Falsework

Formwork and shoring design, erection, concrete placement monitoring and stripping procedures.

Revision 2.1 Updated Apr 19, 2026

Scope and Purpose

This procedure covers building, inspecting, loading, stripping and reshoring formwork and falsework (shoring) for cast-in-place concrete:

applies to the parts it covers (inspection, placement, stripping).

Hazard Identification

  • Formwork or shoring collapse during concrete placement
  • Shore failure from poor bearing (soft or frozen ground, backfill, slab below not able to carry load)
  • Shore buckling (out of plumb, overextended jacks, eccentric load, missing bracing)
  • Tiered single-post shores
  • Wall or column form blowout
  • Overloading the deck (concrete piled, stacked materials, equipment)
  • Premature stripping or reshore removal
  • Falls from deck edges, form faces, openings, walers and ladders
  • Impalement on rebar
  • Rebar mats or cages overturning; wire mesh recoiling
  • Struck by falling panels, tools or materials; crane-handled forms
  • Panels falling during stripping; crane pulling stuck forms
  • Concrete bucket or pump line failure
  • Wet concrete and cement (skin burns, eye damage)
  • Form release agents and curing compounds
  • Silica dust (cutting, grinding, chipping concrete)
  • Power lines (pump booms, cranes, rebar, long tools)
  • Electrical (vibrators, saws, lights in wet conditions)
  • Manual handling of panels, shores, ties
  • Weather: wind on wall forms, cold slowing strength gain, rain undermining sills

Required PPE

  • Hard hat.
  • Safety glasses; face shield when chipping, grinding or where concrete can splash.
  • Safety footwear with toe protection; rubber boots when standing in wet concrete.
  • Leather gloves for handling forms and hardware; alkali-resistant gloves for wet concrete; chemical gloves per the SDS
  • High-visibility apparel where equipment or vehicles move.
  • Full-body harness with lanyard, SRL or positioning device at 4 ft (1.2 m) or more where guardrails are not in place
  • Hearing protection where noise requires it (stripping, saws, vibrators).
  • Respirator where the silica or SDS assessment requires it.

Key Procedure Steps

Design and plan

  1. Get the formwork and shoring design: all vertical loads (forms, concrete, rebar, workers, equipment, impact) and
  2. Keep the drawings, with every revision, on site.
  3. Review the drawings with the crew before erection.
  4. Check what the shores bear on: ground (firm, drained, not frozen) or a slab below (designed or confirmed by the
  5. Plan fall protection, access, the exclusion zone below the pour, crane and pump positions, power line clearance and

Erect

  1. Inspect all shoring components before erection.
  2. Set sills on prepared bearing.
  3. Erect shores plumb and in the drawn positions.
  4. Install bracing as drawn as you go.
  5. Install shore heads and beams with full bearing and no eccentric loading unless designed.
  6. Build wall and column forms with ties and walers at the drawn spacing.
  7. Install guardrails, covers and access as the deck goes up.
  8. Competent person inspects the whole system against the drawings and completes the Section 7 checklist.

Place concrete

  1. Clear and barricade the area below.
  2. Place in the planned sequence, symmetrically, at or below the maximum pour rate.
  3. Nobody under a concrete bucket while it is raised or lowered.
  4. Watch the forms and shoring throughout: deflection, sag, bulging, tie or form movement, joint leaks, shores out of
  5. At any sign of distress: stop the pour, get everyone off the deck and out from below, and call the competent person
  6. After placement, the competent person inspects the shoring again.

Strip and reshore

  1. Do not remove forms or shores (other than for slabs on grade) until the engineer's removal conditions are met, or
  2. Strip in the engineer's sequence.
  3. Support each panel before releasing its ties.
  4. Do not remove reshores until the concrete they support can carry its weight and all loads on it.
  5. Remove nails and tie ends; stack forms and hardware away from edges and walkways.
  6. Inspect components after stripping.

Each step is shortened to its first sentence. The full procedure, with every condition, checklist and sign-off field, is in the PDF.

Training Requirements

  • Formwork carpenter: Trained in the hazards of this work and the rules that apply (US 1926.21(b)(2)); reading and building to the formwork drawings; the system's manufacturer instructions; fall protection training (US 1926.503; Canada federal 12.2, including the fall-protection plan).
  • Competent person (formwork): Experience building and inspecting the system in use; trained on the drawings, inspection points, pour monitoring and stop criteria; appointed by the employer.
  • Concrete placing crew, pump and bucket operators: Briefed on the pour rate, sequence, load limits, stop signal and escape routes for this pour; equipment-specific training.
  • Shoring watch: Knows the warning signs (Section 8, step 17), the stop signal and the escape route.
  • Formwork engineer / designer: Licensed engineer where the company floor or your jurisdiction requires a seal; otherwise qualified by training and experience in formwork design.

Regulatory References

  • 29 CFR 1926 Subpart Q, Concrete and Masonry Construction: 1926.700 (definitions), 1926.701 (general: construction
  • 29 CFR 1926.501(b)(5), 1926.502, 1926.503 (fall protection).
  • 29 CFR 1926.21(b)(2) (safety training).
  • 29 CFR 1904.39 (reporting to OSHA).
  • COHSR SOR/86-304: Part II 2.12, 2.13 (guardrails, toe boards); Part III 3.1 to 3.9 (temporary structures); Part XII
  • Provincially regulated work: your province's OHS regulation for formwork, falsework and shoring.

Download the Full PDF Template

Get the complete Formwork and Falsework document as a fillable PDF, part of the Safe Work Procedures Template Pack.

Get Template Pack

Get This SWP + 4 More Free

Choose from 112 procedures. No credit card, no commitment.

Pick Your 5 Free SWPs

Want Digital Sign-Off for Your SWPs?

Make Safety Easy lets your crew acknowledge procedures on any device. Track who read what, when. No more lost paper forms.

Start Your Free Trial