Masonry and Bricklaying

Masonry construction safety including limited access zones, scaffold loading and silica controls.

Rev 02 Updated Apr 19, 2026

What This Procedure Covers

  1. Plan the wall and sequence

    For brick, block, stone or veneer installation to an approved design. Identify the wall type, construction sequence, temporary support and access arrangements. This procedure is not a structural design or a scaffold erection plan.

    Plan all stages, including incomplete work: Address stability before permanent support is complete and during breaks or overnight. Coordinate with other trades so access, loading, vibration and wind do not defeat the support plan. Stop if the required support or exclusion area cannot be maintained.

  2. Support walls and restrict access

    Use the applicable jurisdiction requirements and approved temporary-support plan. Define the restricted area before construction and communicate who may enter, when and for what work.

    Federal OSHA example: verify local applicability: Under 29 CFR 1926.706, establish the limited-access zone on the unscaffolded side before wall construction, extending the intended wall height plus four feet along its full length. Restrict entry to workers actively engaged in constructing that wall. Walls over eight feet require adequate bracing unless otherwise adequately supported against overturning and collapse. Required bracing remains until permanent supports are in place. Apply the rule's zone-removal conditions and any different state or local requirements.

  3. Provide access and manage loads

    Use a scaffold or platform suited to the combined weight of workers, tools, mortar and masonry units. Confirm load limits and material locations rather than assuming a standard scaffold rating is sufficient.

    Arrange materials around the worker: Use mechanical delivery aids and practical storage positions to reduce repeated carrying, bending and twisting. Check actual unit weights and the number of lifts. Adjust work height where possible rather than repeatedly laying above the shoulder or below the knees. Keep materials within approved loading areas and clear of access routes. Do not climb scaffold cross-braces or improvise platforms on loose blocks. Refer platform changes to the authorized scaffold team.

  4. Match silica controls to the task

    Identify cutting, grinding, drilling and cleanup tasks separately. Select the applicable exposure-control route and document the tool, control system, work location and duration. Do not treat every saw and grinder as one Table 1 task.

    A respirator is not a substitute for failed controls: For federal OSHA Table 1 handheld masonry-saw work, use the specified integrated continuous water delivery and the applicable respiratory protection for location and duration. Dust extraction is not automatically an interchangeable Table 1 option for that task. If the specified control method is not fully implemented, use the standard's applicable exposure-assessment and control route. Do not simply continue with a P100 mask. Stop for loss of water or extraction and restore the approved controls.

  5. Install and inspect

    Follow the design and approved method for units, reinforcement, ties, mortar, grout and sequencing. Check hold points before covering work or increasing wall height. Do not remove braces to make access easier.

    Protect skin and maintain housekeeping: Use suitable alkali-resistant protection and clean washing facilities for wet mortar. Prevent material entering gloves or boots and follow SDS first-aid instructions after exposure. Keep work surfaces clear of offcuts and mortar without creating airborne dust during cleanup. Stop for wall movement, damaged bracing, unsafe loading or conditions outside the approved plan. Clear the affected area and have the condition assessed before work resumes.

  6. Leave safe and record

    Secure unfinished work and maintain required barriers and support. Record the state of the wall, outstanding inspections and who can authorize further work or support removal.

Reference guidance: OSHA 1926.706 and handheld-power-saw silica factsheet; HSE blocks and masonry manual handling and cement guidance. Verify applicable local requirements and obtain project-specific approval.

Download the Full PDF Template

Get the complete Masonry and Bricklaying document as a fillable PDF, part of the Safe Work Procedures Template Pack.

Get Template Pack

Get This SWP + 4 More Free

Choose from 112 procedures. No credit card, no commitment.

Pick Your 5 Free SWPs

Want Digital Sign-Off for Your SWPs?

Make Safety Easy lets your crew acknowledge procedures on any device. Track who read what, when. No more lost paper forms.

Start Your Free Trial