Post-Tensioning Operations
Post-tensioning stressing operations with exclusion zones, calibration and grouting safety.
Scope and Purpose
This procedure covers post-tensioning (PT) of cast-in-place concrete: handling and placing tendons and anchorages, stressing with hydraulic jacks, seating wedges, cutting strand tails, grouting bonded tendons, protecting anchorages, and detensioning or cutting tendons in existing PT structures.
Covers unbonded (single-strand) and bonded (multi-strand, grouted) systems in slabs, beams, walls, and similar members.
Hazard Identification
- Strand, wedge, anchor or jack part released at speed if a strand breaks, wedges slip or the anchorage or concrete fails
- Concrete blowout at the anchorage (concrete too weak, honeycomb, voids)
- Jack overload or hydraulic failure; hose whip; oil injection
- Crushing between the jack and the anchorage or form
- Falls from slab edges and stressing platforms
- Impalement on rebar and tendon supports
- Overloading or early stripping of shored slabs
- Cement grout burns and eye injury; grout under pressure blowing out of vents or hoses
- Cutting strand tails or tendons (sparks, stored energy)
- Future strike on a tendon (coring, drilling, saw cutting, demolition)
- Manual handling of coils, jacks and anchors
- Noise (pump, grinder, saw)
Required PPE
- Hard hat. US: ANSI Z89.1 (1926.100). Canada federal: CSA Z94.1 or ANSI Z89.1 (COHSR 12.1).
- Safety glasses with side shields at all times (US 1926.102(a)(2); Canada federal CSA Z94.3, COHSR 12.12).
- Face shield over safety glasses for the stressing crew during stressing and seating, and for grouting crews (company rule).
- Safety footwear with toe protection (Canada federal CSA Z195, COHSR 12.11).
- Heavy work gloves for strand handling; alkali-resistant gloves for grouting.
- Long sleeves and long pants; no loose clothing near the jack.
- Full-body harness and lanyard where edge protection is removed for stressing (Fall Protection SWP-004).
- Hearing protection where noise requires it.
- High-visibility apparel where vehicles or equipment move (Canada federal CSA Z96, COHSR 12.17).
Key Procedure Steps
Before stressing
- Check tendon profiles, supports and anchorages against the approved shop drawings before the pour.
- After the pour, get written confirmation from the engineer that the concrete has reached the strength set for stressing.
- Strip the stressing pockets.
- Inspect the jack, pump, hoses and gauge.
- Set the stressing zone: barriers and signs at both ends of the tendon, "DANGER - POST-TENSIONING IN PROGRESS - KEEP OUT".
- Set fall protection at the slab edge.
Stressing
- Attach the jack per the PT supplier's procedure.
- Stand to the side of the jack.
- Stress in the sequence and to the force or gauge pressure on the stressing record.
- Record gauge pressure and measured elongation for every tendon.
- Compare elongation with the calculated value.
- Seat the wedges and release pressure slowly per the supplier's procedure.
- Stop at once if a strand breaks, wedges slip, the anchorage moves, concrete cracks or spalls at the anchorage, the jack or hose fails, or anyone enters the stressing zone.
After stressing
- Cut strand tails only after the engineer accepts the elongations, using the method the PT supplier specifies.
- Protect anchorages and fill stressing pockets per the specification.
- Remove barriers only when stressing and tail cutting in that area are finished.
- Remove shores and reshores only when the engineer's conditions are met or strength tests show the concrete can carry its weight and loads (US 1926.703(e)).
Grouting (bonded systems)
- Grout within the time the engineer specifies, with grout that meets the specification.
- Lock out the mixer and pump before cleaning or clearing them (SWP-001).
- Pump from the low point.
- Cap vents when grouting is complete.
Records and future work
- Keep the stressing record and as-built tendon layout for the owner, for the life of the structure.
- Before any coring, drilling, saw cutting, anchoring or demolition in PT concrete: locate and mark tendons by drawings and scanning, and get written approval from the engineer.
Each step is shortened to its first sentence. The full procedure, with every condition, checklist and sign-off field, is in the PDF.
Training Requirements
- Stressing crew: Trained by the PT supplier (or an employer's qualified trainer) on this system's jack, pump, gauge, wedges, stressing record and elongation measurement.
- Supervisor / PT foreman: All of the above, plus stressing sequence, stressing zone control, and what to do when results are out of tolerance.
- Grouting crew (bonded systems): Grout mixing and pumping per the grout specification; vent and pressure procedure; cement burn first aid; lockout of mixer and pump.
- All workers on the deck: PT hazard awareness: what the stressing zone signs mean, stay out of line with anchorages, no cutting or drilling into PT concrete.
Regulatory References
- 29 CFR 1926.701 (general requirements for concrete, incl. (c) post-tensioning operations, (a) construction loads, (b) reinforcing steel).
- 29 CFR 1926.702(j) (lockout of concrete equipment); 1926.703(e) (removal of forms and shores).
- 29 CFR 1926.305 (jacks, incl. hydraulic); 1926.302(d) (hydraulic power tools).
- 29 CFR 1926.100, 1926.102 (head, eye and face protection); 1926 Subpart M (fall protection).
- 29 CFR 1904.39 (reporting).
- COHSR SOR/86-304: Part XII (PPE; fall protection 12.07), Part XV (hazardous occurrence reporting), Part XIX (hazard prevention program and training).
- Provincially regulated work: follow your province's construction regulation.
Download the Full PDF Template
Get the complete Post-Tensioning Operations document as a fillable PDF, part of the Safe Work Procedures Template Pack.
Get This SWP + 4 More Free
Choose from 112 procedures. No credit card, no commitment.
Pick Your 5 Free SWPsWant Digital Sign-Off for Your SWPs?
Make Safety Easy lets your crew acknowledge procedures on any device. Track who read what, when. No more lost paper forms.
Start Your Free Trial