Window and Curtain Wall Installation

Window and curtain wall installation with glass handling, fall protection and wind limits.

Rev 02 Updated Apr 19, 2026

What This Procedure Covers

  1. Plan the assembly and installation

    For the specified window, storefront or curtain-wall system. Use approved drawings and the manufacturer installation sequence. Identify panel weights, handling requirements, anchors and temporary support before delivery.

    Coordinate the whole route: Check unloading, storage, lifting and final placement. Account for glass breakage, wind, obstacles, floor capacity and people below. Do not improvise the installation sequence or rely on an unfinished panel as edge protection.

  2. Protect edges and people below

    Provide the appropriate platform, edge protection or designed personal fall-protection system before work. Confirm anchors, equipment compatibility, clearance and rescue arrangements through the approved plan.

    An exclusion area is not fall protection: Do not use a controlled-access zone as permission to install curtain wall without required fall protection. OSHA's March 2, 2010 curtain-wall interpretation applies Subpart R to the work it addresses and rejects controlled-access or controlled-decking-zone exceptions for that installation. Size and position barriers for the assessed fall and breakage hazards, building geometry and lifting operation. A generic six-feet-per-floor rule is not a design. Secure tools and loose components by the approved method.

  3. Receive, store and inspect panels

    Use suitable racks and handling aids, with support and restraint suited to the units. Confirm floor loading and a clear route before unloading. Keep people out of the path of a falling or tipping panel.

    Select handling equipment for the actual load: Confirm the lifter rating for panel weight, dimensions, surface, orientation and planned movement. A blanket rule to double the panel weight does not replace the manufacturer selection criteria. Do not use a vacuum lifter on damaged glass or an unsuitable surface. Use task-appropriate hand, arm, eye and foot protection. Plan where hands can safely guide the unit without entering crush points. Keep access routes free of offcuts and packaging.

  4. Verify lifting and weather controls

    Complete the specified lifter inspection and functional tests before use. Check pads, hoses, power supply, gauges, alarms, retention systems and any required secondary protection.

    Use the lift plan's environmental limits: Wind acting on a panel can add load and make it difficult to control. Set limits from the lifter, lifting machine, panel and site assessment, including gusts and conditions at installation height. Do not assume generic 20/30-mph thresholds are suitable. Keep people clear of suspended panels and monitor the required lifter indicators throughout movement. Stop for a warning, loss of communication or changing conditions and follow the approved recovery method.

  5. Secure before releasing the lifter

    Position the unit using the approved method, supports and edge clearances. Verify required anchors and temporary restraints are effective before unloading or releasing the lifting device.

    Distinguish structural and weather seals: Use the specified sealant, preparation and curing requirements for each joint. Do not assume a weather seal provides structural support or that uncured structural sealant can carry the panel. Complete the design hold points and record acceptance. Prevent access to incomplete or unsecured units. Mark transparent installations where people could mistake them for an opening, following the project requirements. Maintain temporary protection until authorized removal.

  6. Handover and local additions

    Record the installed condition, outstanding checks and responsibility for temporary supports. Keep barriers where unfinished work or falling-object hazards remain. Dispose of damaged glass using the approved handling method.

Reference guidance: OSHA curtain-wall fall-protection interpretation (March 2, 2010); HSE vacuum lifting guidance; Wood's Powr-Grip selection and operating guidance. Apply the actual system manuals and project-specific approvals.

Download the Full PDF Template

Get the complete Window and Curtain Wall Installation document as a fillable PDF, part of the Safe Work Procedures Template Pack.

Get Template Pack

Get This SWP + 4 More Free

Choose from 112 procedures. No credit card, no commitment.

Pick Your 5 Free SWPs

Want Digital Sign-Off for Your SWPs?

Make Safety Easy lets your crew acknowledge procedures on any device. Track who read what, when. No more lost paper forms.

Start Your Free Trial