0
Fall Protection

Roofing Operations

Fall protection and safe work practices for roofing operations on low-slope and steep-slope roofs.

Revision 2.1 Updated Apr 19, 2026

Scope and Purpose

This procedure covers roofing work on low-slope and steep roofs: getting on and off the roof, hoisting and storing materials, tear-off and disposal, and applying roofing (built-up and hot asphalt, torch-applied modified bitumen, single-ply, shingles, metal roofing, related insulation, sheet metal and vapour barrier work). It also covers inspection and maintenance trips onto a roof.

Roof types (US 1926.500): low-slope roof = slope of 4 in 12 or less. Steep roof = slope greater than 4 in 12.

Hazard Identification

  • Fall from a low-slope roof edge
  • Fall from a steep roof
  • Fall through a skylight, hatch or roof opening
  • Fall through a fragile or weak deck (rot, corrosion, light-gauge panels)
  • Fall at the ladder-to-roof transition or hoist area
  • Materials or debris falling off the roof
  • Mechanical equipment pulling a worker over the edge
  • Fire from torch-applied roofing
  • Propane cylinder leak or fire
  • Burns from hot asphalt or kettles
  • Asphalt fumes, primers, adhesives
  • Heat stress and sun
  • Cold, ice, frost
  • Wind and lightning
  • Contact with rooftop electrical equipment or power lines
  • Slips and trips (membrane, granules, hoses, debris)
  • Hanging in a harness after a fall

Required PPE

  • Hard hat. US: meets 1926.100. Canada federal: CSA Z94.1 or ANSI Z89.1 (COHSR 12.1). Chin strap on steep roofs and at edges (site rule).
  • Safety glasses with side protection (US 1926.102(a)(2)); Canada federal CSA Z94.3 (COHSR 12.12). Face shield over glasses for hot asphalt and kettle work.
  • Safety footwear with slip-resistant soles (Canada federal CSA Z195, COHSR 12.11).
  • Full-body harness, SRL or energy-absorbing lanyard, rope grab and vertical lifeline as the set-up needs, locking connectors, one anchorage connector per worker. Body belts are not allowed for fall arrest.
  • Gloves: work gloves; heat-resistant gloves for torch, kettle and hot asphalt work.
  • Long sleeves and long trousers for hot work (company rule).
  • High-visibility apparel at ground level where vehicles or equipment move (Canada federal CSA Z96, COHSR 12.17).
  • Knee pads for shingle and membrane work.
  • Sunscreen and water (SWP-084).

Key Procedure Steps

Plan

  1. Competent person walks the roof (Section 7, item 1) and measures the slope.
  2. Choose fall protection for each area (Section 1).
  3. Plan access, hoisting, material storage, debris disposal, torch or kettle use, and the rescue method.
  4. Check the weather forecast.

Access and set-up

  1. Set the ladder on firm footing at about 4 to 1, extending 3 ft (0.9 m) and at least three rungs above the roof edge, tied at the top.
  2. First person up connects to a pre-installed anchor or a ladder-top anchor before stepping onto the roof (company rule), then installs edge protection at the access point.
  3. Cover or guard every skylight and opening before anyone else comes up.
  4. Install guardrails, warning lines and anchors.
  5. Set the hoist area: guardrail, chain or gate across the opening when not hoisting.
  6. Barricade the drop zone below.
  7. Brief the crew: fall protection areas, openings, rescue plan, weather limits, torch and kettle rules.

Work on low-slope roofs

  1. Work inside the warning line without PFAS only where the line is set as in step 8.
  2. Anyone who goes between the warning line and the edge is connected to PFAS or travel restraint the whole time (company rule).
  3. Mechanical equipment is used or stored only inside warning lines or guardrails, or by workers on PFAS.

Work on steep roofs

  1. Connect to the anchor before going onto the slope.
  2. Stay connected while on the slope.

Materials and debris

  1. Keep materials more than 6 ft (1.8 m) from unguarded edges, stable and weighted or tied against wind.
  2. Lower debris by chute, hoist or closed container.

Torch-applied roofing

  1. Supervisor authorizes torch work.
  2. Cylinders upright and secured, regulators and hoses approved and undamaged; leak-check every connection before lighting.
  3. Extinguisher within 20 ft (6 m) of the torch (company floor).
  4. Never leave a lit torch unattended.
  5. Fire watch stays at least 60 minutes after the last torch use (company rule), checks for smoke, heat and smouldering, and reports clear to the supervisor.

Hot asphalt and kettles

  1. Set the kettle on the ground, level, away from building openings, air intakes and exits.
  2. Carry hot material in proper containers, never filled to the brim.

Close-out

  1. Shut off torches and cylinders; cool the kettle; secure materials.
  2. Replace every cover and guardrail.
  3. Remove warning lines and anchors only after everyone is off the edge area.
  4. Remove the barricade only when nothing can fall from above.

Each step is shortened to its first sentence. The full procedure, with every condition, checklist and sign-off field, is in the PDF.

Training Requirements

  • Roofer / anyone working on the roof: Training by a competent person in: fall hazards in the work area; erecting, maintaining, taking down and inspecting the fall protection used; use of guardrails, PFAS, nets, warning lines and safety monitoring; the role of each worker when a safety monitor is used; limits on mechanical equipment on low-slope roofs; handling and storing materials and erecting overhead protection; the Subpart M standards (US 1926.503(a)).
  • Supervisor / competent person: As roofer, plus roof hazard assessment, selection and set-up of fall protection, warning line layout, anchor and clearance checks, inspection and removal from service.
  • Safety monitor / fall hazard zone monitor: Competent to recognize fall hazards; trained on the monitor duties in Section 3.
  • Torch operator and fire watch: Trained on the torch, cylinders, leak checks, the torch-safe method for the product, fire watch duties and extinguisher use (US 1926.21(b)(5) for flammable gases).
  • Kettle tender: Trained on the kettle maker's instructions, temperature control, fire response and hot material burns first aid.
  • Rescue person: Trained on the rescue method and equipment in the plan (SWP-089); first aid and CPR.

Regulatory References

  • US OSHA 29 CFR 1926 Subpart M: 1926.500 (definitions incl. low-slope, steep roof, roofing work, warning line, safety monitoring), 1926.501(a)(2), (b)(3), (b)(4), (b)(10), (b)(11), (c), 1926.502 ((b) guardrails, (c) nets, (d) PFAS, (f) warning lines, (h) safety monitoring, (i) covers, (j)(7) roofing materials), 1926.503 (training); Appendix A to Subpart M (roof widths).
  • US OSHA 29 CFR 1926.452(h), (m) (roof bracket scaffolds, crawling boards), 1926.451(f)(3), 1926.454.
  • US OSHA 29 CFR 1926.1051, 1926.1053, 1926.1060 (ladders).
  • US OSHA 29 CFR 1926.150, 1926.151, 1926.153 (fire protection, fire prevention, LP-gas); 1926.252 (waste disposal, chutes).
  • US OSHA 29 CFR 1904.39, Reporting fatalities, hospitalizations, amputations and losses of an eye.
  • Canada: COHSR SOR/86-304, Part II ss. 2.5, 2.12, 2.13 (openings, guardrails, toe boards), Part III s. 3.11 (portable ladders), Part XII ss. 12.06 to 12.09, 12.14, 12.2, 12.21 (fall protection, fall hazard zones, skin protection, training, records), Part XV (reporting), Part XVII (fire protection equipment), Part XIX s. 19.6 (training) (federally regulated workplaces).
  • CSA Z259 series and ANSI/ASSP Z359 (fall protection equipment); NFPA 241 and the National Fire Code (fire safety during construction). Named only; check the edition your jurisdiction requires.
  • Provincial OHS regulations each have a fall protection and roofing part. Use the one for your province.

Download the Full PDF Template

Get the complete Roofing Operations document as a fillable PDF, part of the Safe Work Procedures Template Pack.

Get Template Pack

Get This SWP + 4 More Free

Choose from 112 procedures. No credit card, no commitment.

Pick Your 5 Free SWPs

Want Digital Sign-Off for Your SWPs?

Make Safety Easy lets your crew acknowledge procedures on any device. Track who read what, when. No more lost paper forms.