Scaffolding Erection and Dismantling
This procedure covers scaffold erection, inspection, use and dismantling.
Scope and Purpose
This procedure covers erecting, inspecting, tagging, using, altering, moving and dismantling supported scaffolds, so that the scaffold stands up, carries its load, and nobody falls from it or is hit by anything falling from it.
Covers:
Hazard Identification
- Fall from the platform or open ends
- Fall during erection and dismantling
- Scaffold collapse (overload, poor base, missing braces, mixed parts)
- Tipping (tall, narrow, eccentric loads, wind)
- Platform failure, planks sliding or tipping
- Unsafe access
- Power lines
- Falling tools and materials
- Vehicles or equipment hitting the scaffold
- Weather: wind, storms, snow, ice
- Working height raised on the platform
- Mobile scaffold rolling or tipping
- Moving a scaffold with workers on it (other than mobile)
- Welding or electrical work from the scaffold
- Manual handling of components
Required PPE
- Hard hat (chin strap for erectors and work at height, site rule).
- Safety glasses.
- Safety footwear with slip-resistant soles.
- Work gloves (erectors).
- High-visibility apparel where vehicles or equipment operate nearby.
- Full-body harness and energy-absorbing lanyard or self-retracting lifeline, compatible connectors, for erectors and dismantlers, and for any user where guardrails are not in place; attached only to an anchor the manufacturer or a qualified person approves.
- Tool lanyards when working over people or public areas (site rule).
- Task PPE (respirator, face shield, hearing protection) per the work done from the scaffold.
Key Procedure Steps
Plan
- Competent person confirms the design (manufacturer's instructions, or a qualified person's design; registered professional engineer above 125 ft, or where ties, loads, sheeting or cantilevers fall outside the manufacturer's tables).
- Check the ground, overhead lines, traffic, and the structure for tie points.
- Competent person decides erector fall protection and access for this scaffold.
Erect
- Hang a red tag at every access point.
- Set mud sills and base plates on firm, level ground able to carry the loaded scaffold without settling.
- Erect frames or posts plumb, level and square.
- Leave the existing platform in place until the next frames are set and braced.
- Install ties, guys or braces as you go, at the planned spacing: whichever is stricter of 3 times the least base width and the manufacturer / OSHA spacing (company rule, section 4).
- Plank each working level fully.
- Install guardrails and toeboards on all open sides and ends before the scaffold is released to anyone other than the erectors.
- Install access as soon as erection allows.
- Competent person inspects, writes the load rating and conditions on the tag, and changes it to green (or yellow with written conditions).
Use
- Check the tag.
- Keep loads within the tag rating.
- Do not lean on or stand on guardrails.
- Do not remove ties, braces, guardrails or planks.
- Stop work for storm, lightning, wind at the company limit, snow or ice.
- Mobile scaffolds: everyone off before moving.
Dismantle and close-out
- Hang red tags.
- Dismantle from the top down, in reverse order of erection.
- Lower components by hand line or gin wheel.
- Inspect components.
Each step is shortened to its first sentence. The full procedure, with every condition, checklist and sign-off field, is in the PDF.
Training Requirements
- Scaffold user: Training by a person qualified in the subject: electrical, fall and falling-object hazards in the work area; how to deal with electrical hazards and use the fall protection and falling-object protection in place; proper use of the scaffold and handling of materials on it; the maximum intended load and capacity; other rules that apply (US 1926.454(a)).
- Erector, dismantler, mover, repairer, inspector: As above, plus training by a competent person in: scaffold hazards; the correct procedures for erecting, dismantling, moving, operating, repairing, inspecting and maintaining this type of scaffold; design criteria, maximum intended load and intended use (US 1926.454(b)).
- Competent person (US) / qualified person (Canada federal): Knowledge, training and experience in scaffold erection, inspection and the manufacturer's instructions for the systems used; appointed by the employer.
- Rescue person / team: Trained on the rescue method and equipment in the plan (SWP-089); first aid and CPR.
Regulatory References
- US OSHA 29 CFR 1926 Subpart L: 1926.450 (definitions), 1926.451 (general requirements: (a) capacity, (b) platform construction, (c) supported scaffolds, (e) access, (f) use incl. (f)(6) power lines, (g) fall protection, (h) falling object protection), 1926.452(a), (b), (c), (w) (pole, tube-and-coupler, fabricated frame, mobile scaffolds), 1926.454 (training).
- US OSHA 29 CFR 1926.502(d) (personal fall arrest systems).
- US OSHA 29 CFR 1910.28(b)(12) (general industry scaffolds follow 1926 Subpart L).
- US OSHA 29 CFR 1904.39, Reporting fatalities, hospitalizations, amputations and losses of an eye.
- Canada: COHSR SOR/86-304, Part II ss. 2.12, 2.13 (guardrails, toe boards), Part III ss. 3.2 to 3.10, 3.13 to 3.15 (temporary structures, scaffolds, protective structures, housekeeping), Part XII ss. 12.06, 12.07, 12.2, 12.21 (fall protection, training, records), Part XV (reporting) (federally regulated workplaces).
- CSA Z797 (access scaffold code of practice), CSA S269.2 (access scaffolding), ANSI/ASSP A10.8 (scaffolding), CSA Z259 series. Named only; check the edition your jurisdiction requires.
- Provincial OHS regulations. Use the one for your province.
Download the Full PDF Template
Get the complete Scaffolding Erection and Dismantling document as a fillable PDF, part of the Safe Work Procedures Template Pack.
Get This SWP + 4 More Free
Choose from 112 procedures. No credit card, no commitment.
Pick Your 5 Free SWPsWant Digital Sign-Off for Your SWPs?
Make Safety Easy lets your crew acknowledge procedures on any device. Track who read what, when. No more lost paper forms.
Start Your Free Trial